Victoria’s new renewables policy, and why it could learn from South Africa

Authors

Original article posted on reneweconomy.com.au.

The Victorian government recently announced a policy to decisively increase the amount of renewable generation in Victoria. The rationale for this policy is that existing federal policies are failing to provide investment certainty in the expansion of renewable production capacity.

The government estimates that meeting its policy will require up to 5,400 MW of new renewable generation to be built over the next nine years. This is equivalent to about 60 per cent of Victoria’s peak demand on the power grid.

[Bald_hills_6][2]
Bald Hills wind farm, Victoria, Australia

Assuming an all-in capital outlay per MW of $2.5 million, meeting this policy could require $13.5 billion of new money. Some significant investment in transmission infrastructure is also likely to be needed. After residential rooftop solar, this will be, by far, the largest investment in new generation capacity in Australia since the creation of the National Electricity Market.

Last month a consultation paper from the Department of Environment, Land, Water and Planning sought responses on various issues (identity of the counter-party, specification of the payment instrument, technology selection, treatment of other subsidies, contract duration and auction design). The Department is currently focusing on the preparation of enabling legislation with a view to conducting its first tender next year.

South Africa’s Renewable Energy IPP Procurement Program (REIPPPP) is an interesting point of reference, of comparable scale, to the Victorian policy. Though there are many differences, many of the important issues are similar and much can be learned from the South African experience. At the least, a quick look at their program we might give a sense of what lies in store for Victoria.

Under the REIPPPP program 6,327MW (of which 3,357 MW of wind in 34 projects, 2,292 of PV in 45 projects, 600 MW of concentrated solar in 7 projects and several much smaller biomass and small hydro projects) have been awarded PPAs. Total capital outlays of around $19bn are expected, to complete these projects. As a result of this, since 2012, South Africa has ranked among the top ten countries globally in terms of renewable energy independent power producer investment.

In the first tender in November 2011, 28 projects offering 1,416 MW in total were selected. In the second round in May 2013, 19 projects offering 1,040 MW were selected. A third round in August 2013 selected 15 projects for 1,321 MW. A fourth round in August 2014 selected 26 projects for 2,207 MW. A fifth round is expected to commence shortly.

The bidders offer prices for 20 year Power Purchase Agreements with Eskom, the government owned national power monopoly. Two additional agreements with the Government underwrite Eskom default risks, provided step-in rights to lenders in the case of default and ensure contractual obligations for delivery of up to 17 economic and social development obligations. Community ownership (at not less than 2.5% of the total project cost) is mandatory and the developer have to come up with ways, such as community trusts, to comply with this. Contract evaluation is based 70% on price and 30% on socio-economic factors.

The contracts are not negotiable and bidders are required to submit bank letters to the effect that financing is locked-in. This effectively outsources due diligence to the lenders. The lenders in turned passed this on to developers but in a way that ensured the duty of care was to lenders.

The 64 successful projects in the first three rounds involved over a 100 different shareholder entities, 46 of these in more than one project. Banks, insurers, development banks, international utilities and direct foreign investors have all participated in the program. The most common financing structure has been project finance, although about a third of the projects in the third round used corporate finance.

The majority of debt funding has been from commercial banks with the balance from development banks, pension and insurance funds. Eighty-six percent of debt has been raised from within South Africa on 15-17 year loans (from Commercial Date of Operation). Debt risk premia in bank loans have been around 450 basis points on top of the South African equivalent to Australia’s 90 day bank bill swap rate.

Forty-nine Engineering, Procurement and Construction (EPC) contractors have been involved in the 64 projects during the first three rounds, the majority in more than one project either as the primary or secondary contractor.

Prominent EPC contractors with three or more projects include Vestas (Danish), Acciona (Spanish), Consolidated Power Projects (South African), Group Five Construction (South African), Juwi Renewable Energies (German), Murray and Roberts (South African), Abengoa (Spanish), ACS Cobra (Spanish), Iberdrola Engineering and Construction (Spanish), Nordex Energy (Germany), Scatec (Norwegian), Suzlon (India), and Temi Energia (Italian). Many of these EPC contractors have set up subsidiary companies in South Africa.

The main suppliers of wind turbines and PV equipment include Vestas, Siemens, Nordex, ABB, Guodian, Suzlon, Siemens, SMA Solar Tech, BYD Shanghai, Hanwha Solar, 3 Sun, AEG and ABB. A local wind tower manufacturing facility and at least five PV panel assembly plants have been established in South Africa.

Over the period of the four bidding rounds, offered prices per MWh halved for wind and concentrated solar and declined by 75% for solar PV. Global technology development, local economies of scale, improving investor confidence and lower transaction costs explain this stunning progress.

As the volume of renewable capacity has increased, transmission connection has been become an increasing concern. Bidders are responsible for connection to the nearest major substation, but augmentation of the shared network is lagging behind and this has become a particular issue for the most recently awarded projects.

The World Bank suggests the most important lesson to transfer from the REIPPPP is the benefits of a well-designed and transparent procurement process. They say that the Department of Energy recognised that it had little capacity to run a sophisticated multibillion-dollar competitive bidding process for renewable energy.

As a consequence, it sought the assistance of the National Treasury’s Public-Private Partnership (PPP) Unit to manage the process. A small team of technical staff from DOE and the PPP Unit established a project office which functioned effectively outside of the formal departmental structure of national government. It was led by a senior manager from the National Treasury PPP Unit and other legal and technical experts were brought on board to form a tightknit team.

This was viewed favorably by both the public and private sector as a professional unit with considerable expertise in closing PPP contracts and a reputation as problem solvers and facilitators rather than regulators. The credibility of this team with the bankers, lawyers, and consultants involved in such projects in South Africa generated enthusiastic participation by private sector players.

The World Bank reports that high standards were set and maintained throughout the bidding process, including security arrangements and transparent procurement procedures. Documentation was extensive, high quality, and readily available. Domestic and international advisers were extensively involved in the design and management of the program, in reviewing bids, and in incorporating lessons learned into the program as it progressed through the bid rounds.

To fund the procurement process, in 2011 the National Treasury provided R100 million (around $10m). The World Bank provided a further US$6m and various bi-lateral donor agencies from Denmark, Germany, Spain and the UK contributed funding for technical assistance. This funding saw the program through the first round and part of the second. Subsequent to that, the program relied on bidder registration fees and fees paid by successful IPP project companies.

Successful project companies must pay a project development fee of one percent of total project costs to a Project Development Fund for Renewable Energy projects managed by the Department of Energy. The fund covers current and future costs associated with procurement of renewable energy and oversight of the program. These funding arrangements have helped the program remain off the formal government budget in subsequent bidding rounds.

Coming back home again, the Victorian Government’s policy marks a major departure in the state’s energy policy. Since privatising the industry a little under twenty years ago, the Government has had a watching brief with some intervention around the edges – most significantly in smart meters. The Government is now getting back into the business of electricity production.

Even if it does not intend to own or operate generators, it is the Victorian Government that will under-write what will be a massive investment program. Surely every large new renewable generator developed in Victoria for the next nine years will be part of its program. If the Government legislates its policy as expected, the Victorian Government will become the most important player in the Victoria’s electricity generation sector.

We all, including the Government, have yet to discover how its policy will unfold in practice.

The South African experience can provide some feeling for what goes into the competitive procurement and development of 6,000 MW of renewable capacity. Their apparent success in this endeavor is encouraging. It would be good to learn from this what we can.

Bruce Mountain is an energy economist and Director of consultancy, CME. Vivienne Roberts is an engineer and accountant and was a technical advisor on a number of projects in South Africa.